DRESDEN NUCLEAR POWER STATION, UNIT 2: NRC Proposes $8,500 Civil Penalty to Alt & Witzig Engineering, Inc.

Penalty

Dresden Nuclear Power Station, Unit 2 issued the following announcement on May 15.

The Nuclear Regulatory Commission has proposed an $8,500 civil penalty against Alt & Witzig

Engineering Inc. for a violation associated with the control of a portable nuclear gauge. The company is

based in Carmel, Ind.

The Oct. 3 violation involved the licensee’s failure to provide physical control of a portable

nuclear gauge, which was stolen from outside the gauge operator’s residence. NRC regulations require

a minimum of two independent physical controls to prevent the unauthorized removal of portable

gauges. The portable gauge was recovered with the licensed material intact.

The NRC conducted an inspection to review the event circumstances, the procedures in place at

the time, associated documentation and the immediate corrective actions that were taken. A follow-up

inspection will be conducted within 12 months of this enforcement action to ensure long-term

corrective actions are effective.

Alt & Witzig officials responded to the violation and now have 60 days to agree to the penalty

or request an appeal.

A copy of the enforcement action will be posted in ADAMS on the NRC website.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS