VILLAGE OF COAL CITY: Broadway Street Reconstruction Update

Local Government

By Press release submission | Aug 14, 2019


Village of Coal City issued the following announcement on Aug. 8.

The contractor has begun roadway excavation and placement of stone subgrade the west side starting at Division Street and working south. Sidewalk on the west side of Broadway will be removed at this time. Curb and sidewalk installation is scheduled to begin after the excavation.

Original source can be found here.

Source: Village of Coal City 