Village of Minooka Public Works Committee met Nov. 19.
Here is the agenda provided by the committee:
1. Public Forum
2. Superintendents Report
• Water
o Kendall Energy used water for cooling
• Sewer
• Streets
o Village Christian Church adopt a highway
• Parks
3. Engineers Report
• Project schedule updates
4. Change order #5 for time extension of MFT contract with Austin Tyler
5. Sanitary sewer flow monitoring study
6. Bid results for 2024 downtown sidewalk snow removal contract
7. WY2024 Water Audit ($18,910)
8. Rapid flashing beacons downtown ($5,956)
9. De-icing salt purchase order ($82,566)
10. Anti-ice system purchase ($44,163)
11. Repair mixer #1 at WWTP ($10,461)
12. Repair mixer #2 at WWTP ($9,833)
13. Replace submersible mixer at WWTP ($16,874.56)
14. Replace submersible pump at WWTP ($14,754)
15. Change order #1 for sanitary sewer televising and cleaning project ($10,986.75)
16. Pay request #1 (partial) for sanitary sewer televising and cleaning ($7,669.35)
17. Pay request #2 (partial) for the WWTP equipment replacement program ($79,083)
18. Change order #2 for the WWTP equipment replacement program ($20,929)
19. Miscellaneous
20. Adjournment
https://events.minooka.com/Village/Detail/2024-11-19-1800-Public-Works-Committee-Meeting2/b511cb6a-9538-4727-abb0-b229016cacee